Demolitions
A demolition notice is required where you intend to demolish any building or part of a building, unless it's due to a council demolition order, a part of an occupied building, a building of less than 50 cubic metres, a greenhouse, conservatory, shed, prefabricated garage or an agricultural building.
Visit the GOV.UK website for legislative information and requirements relation to procedures about demolitions.
How to apply
Please download our application form and email it to us, attaching the following to your email:
- A location plan, clearly indicating the buildings to be demolished, all adjacent properties and existing drainage systems to be sealed
- A copy of the method statement, indicating safe methods of demolition
There will be a charge of £278.40 (inc VAT) to pay, which we'll request on receipt of your application.
Frequently asked questions
What notice time do I need to give?
Work shouldn't be started before you've received a counter notice under section 81 of the legislation from us, or when six weeks have elapsed since the notice was submitted.
What happens if I don’t give notice?
Failure to comply with the legislation regarding demolition under the 1984 Building Act may result in a summary conviction and a fine up to £2,500 (this fine is changeable without prior notice).