Please note that the 'construction' timeframe under 'Stages' above is merely notional for the time being as the programme of work has yet to be published by our contractor.
Scheme description
Design and installation of upgraded traffic signals at the junction (due to equipment at end of serviceable life) with new staggered, controlled 'puffin'-type pedestrian crossing on the Arlington Way approach and inclusion of a ‘no U-turn’ TRO (traffic regulation order) on all four approaches to the junction.
Location
Battlefield Road / Tesco Access / Arlington Way, Harlescott, Shrewsbury Junction, grid ref: 351352, 315922.
What3words ref ///data.taking.depend
On target?
Constructed.
Map
Please note that construction work undertaken can often cover an area rather than one specific place, so the pin on the map on this page is intended as a guide only.
Correspondence history
All relevant correspondence relating to this piece of work will be included here:
Update: 17 January 2024
The Contractor has provided the following dates, 13 and 14 February to commission the MOVA for this scheme. This finalises the construction phase for the scheme.
Contact
Please contact cilproject@shropshire.gov.uk with any comments or queries.
Please note that all queries the teams receive along with the responses will be uploaded onto the portal to provide updated information for everyone. Please don't include any personal or sensitive information as this will need to be redacted.