Bishops Castle town centre - phase 1

Provision of a route study report to improve the highway.

SY9 5BG

Stages

Route study report
Autumn 2023
Design
Autumn 2023 Spring 2024
Construction
Spring 2024

Status

Route study report
Completed
Design
Pending
Construction
Pending

Please note that the 'construction' timeframe under 'Stages' above is merely notional for the time being as the programme of work has yet to be published by our contractor. 

Awaiting contractor programme to be combined with maintenance programme.

Description

Provision of a route study report to improve the highway within Bishops Castle, addressing inappropriate parking conditions, congestion and insufficient disability and cyclist access.

Location

  • B4385 Bull Lane, Bishop’s Castle, Grid Ref. 332502,288998. What3words Ref: ///deflation.global.unlimited
  • C6197 Market Square / Welsh Street, Bishop’s Castle, Grid Ref: 332338,288985. What3words Ref: ///budget.finalist.juror
  • U6136 Kerry Lane, Bishops Castle. Grid Ref: 332195,288495. What3words Ref: ///immediate.mouths.rehearsed
  • U6979 Church Street / High Street, Bishop’s Castle, Grif Ref. 332353,288781. What3words Ref: ///ranks,overheard.scorecard

On target?

Yes.

Map

Please note that construction work undertaken can often cover an area rather than one specific place, so the pin on the map on this page is intended as a guide only.

Correspondence history

All relevant correspondence relating to this piece of work will be included here:

None to date.

Contact

Please contact cilproject@shropshire.gov.uk with any comments or queries.

Please note that all queries the teams receive along with the responses will be uploaded onto the portal to provide updated information for everyone. Please don't include any personal or sensitive information as this will need to be redacted.

Additional Information

Area
South Shropshire