Proceed with selected recommendations from the network efficiency report.

SY9 5BG

Stages

Route study report
Autumn 2023
Design
Spring 2024
Construction
Spring 2024 Spring 2025

Status

Route study report
Completed
Design
Completed
Construction
Pending

Please note that the 'construction' timeframe under 'Stages' above is merely notional for the time being as the programme of work has yet to be published by our contractor. 

This scheme has been prioritised in line with discussions with Shropshire Council, councillors and the town council.

Awaiting contractor programme to be combined with maintenance programme.

Description

Proceed with selected recommendations from the network efficiency report. Actions include revising the priority at the Boars Head intersection to continue along the ‘B’ road instead of using Church Street. Second, installing a raised table across the bottom of U6979 Church Street by the Boars Head junction. Third, install a yellow disabled parking bay outside the pharmacy. 

Location

  • Boars Head intersection (U6979 Church Street / U6136 Union Street / B4385 Station Road / B4384 Church Street), Bishop’s Castle, grid reference 332336, 288654
  • U6979 Church Street, Bishop’s Castle, grid reference 332356, 288801

On target?

Pending.

Map

Please note that construction work undertaken can often cover an area rather than one specific place, so the pin on the map on this page is intended as a guide only.

Correspondence history

All relevant correspondence relating to this piece of work will be included here:

None to date.

Contact

Please contact cilproject@shropshire.gov.uk with any comments or queries.

Please note that all queries the teams receive along with the responses will be uploaded onto the portal to provide updated information for everyone. Please don't include any personal or sensitive information as this will need to be redacted.

Additional Information

Area
South Shropshire