Cross Houses to Atcham improvements

The scheme aims to design and implement a package of highway intervention works.

SY5 6JJ

Stages

Design
Winter 2023 Summer 2024
Construction
Spring 2024 Spring 2025

Status

Design
In progress
Construction
Pending

Please note that the 'construction' timeframe under 'Stages' above is merely notional for the time being as the programme of work has yet to be published by our contractor. 

Description

The scheme aims to design and implement a package of highway intervention works in the villages of Atcham and Cross Houses, including reducing the speed limit along the A458 (through Cross Houses), reducing the speed limit and introducing a weight restriction along the country lane connecting the two villages; revising the signage.

Location

Cross Houses (A458) / Atcham (B4380) / Lane (C5062). Grid ref: 353740, 307531 and 353953, 309334.

What3words Ref: ///salary.sides.awkward to ///cold.novelists.post

On target?

Yes.

Map

Please note that construction work undertaken can often cover an area rather than one specific place, so the pin on the map on this page is intended as a guide only.

Correspondence history

All relevant correspondence relating to this piece of work will be included here:

April 2024

Initial design completed winter 2023, shared with Berrington Parish Council January 2024, awaiting feedback from Atcham Parish Council.

Contact

Please contact cilproject@shropshire.gov.uk with any comments or queries.

Please note that all queries the teams receive along with the responses will be uploaded onto the portal to provide updated information for everyone. Please don't include any personal or sensitive information as this will need to be redacted.

Additional Information

Place plan project
778
Area
Central Shropshire