Carreg-y Big junction to Barkers Hill junction, Selattyn
- Contractor - Severn Trent Water
- Duration - 41 working days. 57 calendar days
- Description of work - From outside entrance to Barkers Hill Reservoir to junction with C1006, burst driven mains renewal of approx 680m. HDD, test, chlorinate, commission & transfer services.
backfill, reinstate and move T/M. Excavate HDD pits and trial hole on any crossings. Prep work on services, bringing them out of privates. - More information on One Network