Meole Brace Footbridge

Refurbishment works.

SY3 9JU

Stages

Stage 1
Stage 2

Status

In progress

Shropshire Council, together with Alliance partners Kier and WSP, are planning to carry out refurbishment works to Meole Brace Footbridge. To undertake the works and maintain the pedestrian route, the existing bridge is to be removed for refurbishment, and a temporary pedestrian footbridge installed. A combination of lane and full road closures will be required to complete this scheme, which are outlined below.

Stage 1: 19 May – 27 May 2025

Date

Monday 19 May to Thursday 22 May

Traffic management

Closure of Footbridge and Single lane closure Northbound over Meole Brace road bridge between the hours of 8pm and 6am

Works

preparation work to the footbridge to include :

  • Tree removal
  • Embankment works
  • Footbridge jacking
Date

Friday 23 May to Saturday 24 May

Traffic management

Closure of Footbridge and 24hr Single lane closure Northbound over Meole Brace road bridge.

Works

Final freeing of the footbridge ready for lift out Saturday night.

Date

Saturday 24 May to Sunday 25 May

Traffic management

Closure of Footbridge and Full road closure to Meole Brace bridge between 8pm and 8am

Works

Lift out of existing bridge and removal from site for refurbishment, installation of temporary footbridge.

Date

Sunday 25 May to Tuesday 27 May

Traffic management

lane closure Northbound over Meole Brace road bridge between the hours of 8pm and 6am

Works

Contingency closures, to allow completion of works, to temporary bridge.

Stage 2: 20 June 2025 – 25 June 2025

Date

Friday 20 June to Saturday 21 June

Traffic management

Closure of Footbridge and 24hr Single lane closure Northbound over Meole Brace road bridge.

Works

Enabling works to temporary footbridge, in preparation for lift out

Date

Saturday 21 June to Sunday 22 June

Traffic management

Closure of Footbridge and Full road closure to Meole Brace bridge between 8pm and 8am

Works

Lift out of temporary bridge and installation of refurbished original footbridge.

Date

Sunday 22 June to Monday 23 June

Traffic management

Closure of Footbridge and Single lane closure Northbound over Meole Brace road bridge between the hours of 8pm and 6am

Works

Completion of reinstatement works, pedestrian barriers and approach footways

Date

Monday 23 June to Wednesday 25 June

Traffic management

lane closure Northbound over Meole Brace road bridge between the hours of 8pm and 6am

Works

Contingency closures.

The works have been programmed to provide the minimal impact to local users, with closures taking place outside of peak hours wherever possible and signed diversion routes in place (see attached).

Shropshire Highways have endeavoured to communicate with local elected members and business in the area, with further communication throughout the works, where changes are required.

We apologise for any inconvenience these works may cause.

Please note that the map on this page may not show the precise location of the work, and is intended as a guide only.