Pound Lane to Shrewsbury Rd, Pontesbury

National Grid work

SY5 8JR

Duration

  • Contractor - National Grid
  • Duration - five working days
  • Description of work - install duct and associated chambers for a 33 kV single circuit cable route (with telecoms) between Bayston Hill 33 kV Substation and Malehurst 33 kV Substation

Please note that the map on this page may not show the precise location of the work, and is intended as a guide only.

Additional Information

Road closure?
Yes
Footway closure?
No