Key dates/timeline
Work is due to be carried out by 'zone' on the dates stated below. Please note that these dates are projections and are subject to change:
- Zone 1 – June 2024 – September 2024
-
Zone 2 - September 2024 – February 2025
-
Zone 3 – February 2025 – April 2025
-
Zone 4 – April 2025 – May 2025
-
Zone 5 – August 2024 – November 2024
-
Zone 6 – October 2024 – February 2025
-
Zone 7 – January 2025
-
Zone 8 – February 2025
-
Completion expected June 2025