Mytton Estate, Shawbury

The scope of this scheme is to design and implement a road safety improvement scheme.

SY4 4NZ

Stages

Design
Autumn 2023
Construction
Summer 2026

Status

Design
Completed
Construction
Pending

Description

The scope is to design and implement a road safety improvement scheme along the length of the A53 situated between Shawbury and Edgebolton, including a revision to the signage and road markings.

VAS installation outstanding, awaiting contractor programme.  

Construction to proceed in August subject to permit approval.

Correspondence history

All relevant correspondence relating to this piece of work will be included here:

None to date.

Contact

Please contact cilproject@shropshire.gov.uk with any comments or queries.

Please note that all queries the teams receive along with the responses will be uploaded onto the portal to provide updated information for everyone. Please don't include any personal or sensitive information as this will need to be redacted.