Description
Proposals seek to improve pedestrian movements within Pontesbury. Measures include junction realignment, widening footways and road safety measures.
- Phase 1 - drainage measures on Brookside to include a raised table and pavement realignments to help aid drainage to watercourse
- Phase 2 – footway widening to the junction along Hall Bank, to also include a suggested pedestrian facilities to aid movements
- Phase 3 – realignment of the Main Road junction and pedestrian facilities, discussions being held with parish council on scope of works for delivery at a future date. Original proposals revisited following previous public meeting, new concept design prepared and shared with the parish council
Map
Please note that construction work undertaken can often cover an area rather than one specific place, so the pin on the map on this page is intended as a guide only.
Correspondence history
All relevant correspondence relating to this piece of work will be included here:
None to date.