The Coppice / Clayton Way Footway, Shrewsbury

The scheme aims to provide a new connecting footway.

SY3 5DD

Stages

Design
Spring 2024 Autumn 2024
Construction
Autumn 2024 Spring 2025

Status

Design
Pending
Construction
Pending

Description

The scheme aims to provide a footway connecting the Coppice Extra Care Housing and Clayton Way to enable residents a more direct route to local amenities within Shrewsbury. 

Currently on hold

Location

  • Clayton Way, Shrewsbury. Grid ref: 345933, 313728. What3words Ref: ///flanked.interacts.prayers
  • The Coppice Extra Care Housing. Grid ref: 346187, 313891. What3words Ref: ///promoted.disprove.parrot

On target?

Yes.

Map

Please note that construction work undertaken can often cover an area rather than one specific place, so the pin on the map on this page is intended as a guide only.

Update - 14 July 2026

Awaiting information and decision regarding the Oxon Link Road, this may impact design scope. 

Correspondence history

All relevant correspondence relating to this piece of work will be included here:

None to date.

Contact

Please contact cilproject@shropshire.gov.uk with any comments or queries.