2025/26 bridge maintenance programme
- Bridge name / description
- Betton Street Railway Footbridge
- Bridge number
- B5091
- URS no.
- F4085/ 10
- OSGR or postcode
- SJ 499 118
- Works description
- Remove Redundant Structure over Shrewsbury to Hereford Line. Slip in programme due to ongoing correspondence with NR regarding availability of possession dates and delay damage costs.
- Planned date of work
- Postponed until 2026/27
- Bridge name / description
- Montague Street Railway Footbridge
- Bridge number
- B5234
- URS no.
- F4072/ 10
- OSGR or postcode
- SJ 497 113
- Works description
- Maintenance of sub-standard bridge elements . Budget Construction Costs to be confirmed. Slip in programme due to ongoing correspondence with NR regarding availability of possession dates and delay damage costs..
- Planned date of work
- Postponed until 2026/27
- Bridge name / description
- Greyfriars Footbridge
- Bridge number
- B5900
- URS no.
- F4007/ 10
- OSGR or postcode
- SJ 494 121
- Works description
- Encapsulation of structure, abrasive blasting of paint back to metal, painting of structure, replacement of service hanger and sealant of top hat void. Resurfaced with Tar modified resin slurry.
- Planned date of work
Postponed until June - July 2026/27
- Bridge name / description
- Meole Brace Footbridge
- Bridge number
- B5328
- URS no.
- A5191/ 10
- OSGR or postcode
- SJ 490 107
- Works description
- Removal of exiting footbridge for major refurb - steelwork painting and re-decking. Installation and removal of temporary footbridge
- Planned date of work
May- June 2025
Completed - Sept 2025
- Bridge name / description
- Nant Lane Retaining Wall
- Bridge number
- Divisional Wall
- URS no.
- U0119/ 15
- OSGR or postcode
- SO 581 746
- Works description
- Collapsed section of retaining wall circa 15 square metres. Retaining wall to be repaired/ rebuilt.Road closure currently inplace.
- Planned date of work
Postponed until 2026/27
- Bridge name / description
- Rindleford Footbridge
- Bridge number
- B4901
- URS no.
- U7115/ 10
- OSGR or postcode
- SO 737 955
- Works description
- 4-span RoW Footbridges with failed sections to spans 1, 2 and 3. Listed status and SC HE will not allow the structure to be de-listed. Need to close footpath (H&S) grounds and look to remove the redundant structures as interim position to assess the structure. Dismantle superstructure and re-build Footbridge with new timber beams, cast iron trough units (reused), cast iron handrails, and asphalt surfacing.
- Planned date of work
Postponed until 2026/27 due to Environmental Agency delays in processing
- Bridge name / description
- Corve Culvert
- Bridge number
- B6305
- URS no.
- B4361/ 65
- OSGR or postcode
- SO 510 753
- Works description
- Undertake concrete repairs to the soffits and deck of the culvert, construct new concrete slab over culvert with a waterproofing layer, resurfacing of carriageway.
- Planned date of work
Planned for 2025/26
Completed - Sept 2025
- Bridge name / description
- Rhyd Meredith
- Bridge number
- B1201
- URS no.
- A495/ 10
- OSGR or postcode
- SJ 251 225
- Works description
- Reinstate / build formal stone revetment to RHS and face with large stones
- Planned date of work
Postponed until 2026/27 due to Environmental Agency delays in processing applications
- Bridge name / description
- Holbrook Coppice
- Bridge number
- B3285
- URS no.
- A4169/ 95
- OSGR or postcode
- SJ 653 051
- Works description
- Construction of access ramp down to upstream end of culvert in order to allow maintenance to clear grills of debris and silt to include construction of (maintenance steps)
- Planned date of work
- Planned for 2025/26
- Bridge name / description
- Hope Valley Embankment Slip.
- Bridge number
- A488
- URS no.
- A488/361
- OSGR or postcode
- SJ350 017
- Works description
- Embankment Slips adjacent to Minsterley Brook (Rea Brook). Earth retaining wall system, slope stabilisation. Temporary traffic lights installed as temporary measure.
- Planned date of work
Planned for July 2025
Completed - Sept 2025
- Bridge name / description
- Bronygarth Bridge
- Bridge number
- B1406
- URS no.
- C1001/ 10
- OSGR or postcode
- SJ 268 369
- Works description
- Clear 5 m wide access point to downstream end of the structure. Install mass concrete base to scoured areas up to 2m wide to secure structure. Remove surcharge from top of carriageway, rebuild masonry spandrels, wing wall and parapet Backfill carriageway and surface
- Planned date of work
Planned for August 2025/26.
*UPDATE* - planned for Sept 2025/26 for a duration of 17 weeks.
- Bridge name / description
- A490 Chirbury to Churchstoke Embankment Slip
- Bridge number
- A490
- URS no.
- A490/40
- OSGR or postcode
- SY15 6DS
- Works description
- Hard engineered piling solution required to fix 25m section of slipped embankment. Temporary/permanent traffic lights installed as temporary measure whilst solution is being completed.
- Planned date of work
Postponed until 2026/27
- Bridge name / description
- Cardington North Bridge
- Bridge number
- B5749
- URS no.
- U5315/ 10
- OSGR or postcode
- SO 507 955
- Works description
- Installation of a structural liner, repairs to masonry arch and carriageway surfacing
- Planned date of work
- Planned for August / Sept 2025
- Bridge name / description
- Grove Farm Culvert
- Bridge number
- Divisional Culvert
- URS no.
- U5315/ 10
- OSGR or postcode
- SO 505 950
- Works description
- Like for like repair to maintain existing orifice size, with concrete abutments, arch and invert. Existing road closure is place following the collapsed to the downstream end of the culvert
- Planned date of work
Planned for 11 August 2025 for three weeks.
Completed - Sept 2025
- Bridge name / description
- Boreton Ford Footbridge
- Bridge number
- B5909
- URS no.
- U5838/ 20
- OSGR or postcode
- SJ 503 064
- Works description
- Footbridge replacement
- Planned date of work
Planned for summer 2025.
Completed - July 2025
- Bridge name / description
- Chapel Lawn Retaining Wall
- Bridge number
- Divisional Retaining Wall
- URS no.
- C6208/ 25
- OSGR or postcode
- SO 311 764
- Works description
- Retaining wall to support the collapsed embankment, underpinning to scoured sections of existing retaining wall
- Planned date of work
Planned for 11 September 2025 for three weeks
- Bridge name / description
- A4117 From Station Road End To Hereford And Worcester County Boundary Lem Hill, Cleobury Mortimer (Baveney Culvert)
- Bridge number
- Divisional Culvert
- URS no.
- A4117
- OSGR or postcode
- Works description
- Reconstruction of collapsed headwall. Temporary traffic lights installed as temporary measure whilst design solution is being completed.
- Planned date of work
Postponed until 2026/27