Section 38 and Section 278 application process

Section 38 and Section 278 application fee

As of 1 April 2025, all Section 38 and Section 278 Agreements will be subject to a £5000.00 application fee.

Shropshire Council - Internet Payments

Search 'Highways – Legal Agreements'. 

Please note, Section 38 and Section 278 Technical approval process will not commence until application form has been submitted and appropriate fee paid.

Section 38 application form

Complete Section 38 form

Please provide all information requested. Technical approval process will not commence until all fees have been paid and all information required for the Section 38 Technical approval process to complete. 

Section 278 application form

Complete Section 278 form

Please note we do not accept WeTransfer or Drop box on completion of application form and application fee and link will be shared to upload drawings. 

Fees

Find out more about the fees and charges

Fees and charges

Checklists

Highway drainage easement drawings 

  • Shows clearly and precisely, by suitable colouring/colour edging, the precise extent of the land to be searched – ie to be subject to the deed of grant of easement
  • Has been drawn accurately to a stated scale and shows the scale to which it's drawn – preferred scales are: (a) 1:1250 – 1:500 for urban properties (b) 1:2500 for rural properties (fields and farms etc)
  • Shows sufficient detail to be identified on the Ordnance Survey map and/or grantor’s, lessor’s or vendor’s title plan
  • Clarifies its general location by showing roads, road junctions or other landmarks
  • Shows its orientation (for example, a north point)
  • Is based on a scale of metric measurement and includes a bar scale
  • Ideally, is not marked as 'for identification only' or similar wording
  • Isn't endorsed 'Do not scale from this drawing' or any similar phase or includes a statement of disclaimer intended to comply with the Property Misdescriptions Act 1991
  • Our legal department suggest that the land to be subject to deeds of grant of easement be hatched and edged in solid brown, with the drainage apparatus being shown by blue colouring. The proposed highway land which is to take the benefit of the easement should be coloured pink (as per the Section 38 plan) with any existing highway
  • Coloured pink and edged red. All other colouring that may be shown on the plan should be removed – ie this may be a site boundary edged red/green etc
  • A separate plan will be required for each easement area that may fall within separate titles – i.e. where the easement crosses over several different land ownerships. The full extent of the proposed highway should be coloured pink on each of these plans. This pink colouring is required to be bold enough to be clearly shown when the plan is printed as a paper copy

In addition to the above in order to progress the Section 278 Agreement Shropshire Council will require the following:

  • Site boundary plan – extent of site to be edged red on plan, to indicate extent of planning application associated with the works
  • Up-to-date Land Registry title registers and plan to be provided in respect of the development land
  • Description of the works to be carried out, which will form part of the wording of the Section 278
  • A returnable deposit of £5000 will be required to cover cost of works as detailed within the Section 278 agreement for the provision of any works required to be undertaken by the council in the interest of highway safety
  • Breakdown of costs of works to inform the bond level
  • Details of commuted sums (if required)