Updates
Works in the Cross Street tunnel
Works in the Cross Street tunnel will start on the evening of Tuesday 1 April (rather than 31 March as previously advised). The tunnel closure will be in place from approximately 8pm through to 6am each night until the morning of 4 April. The tunnel will be open at all other times between those dates.
Subsequent night closures will then continue from Sundays to Thursdays (inclusive) through to the end of the month, again from approximately 8pm to 6am. This means that no works will take place on Fridays or at the weekends; this is intended to ease the impact of the works on the lead up to and including weekends, plus the bank holiday, enabling resources from the contractor and site team to be planned appropriately.
These changes follow discussions between the council’s highways and public protection teams.
The work on Cross Street will include widening of the existing footpath, and construction of a new footpath under the bridge, for improved pedestrian access. This is all part of the improvements being made to the station gyratory area.
In conjunction with the closure of the tunnel on the evening of 1 April, two-way traffic on Chester Street will be introduced, which is part of the permanent requirements of the project. On opening the tunnel on the 2 April:
- A single lane will be in place through the tunnel, but the right turn on to Castle Foregate won't be available
- If you're travelling from Ellesmere Road wishing to access the rail station, town centre, or Smithfield Road you should use Chester Street
- If you're travelling from Smithfield Road or Ellesmere Road wishing to access the routes towards Heathgates or Howard Street you'll be able to turn left or travel straight ahead on exiting the tunnel.
There will be four nights early on in the programme when site activities are expected to be noisy. This will be due to cutting the road surface, and breaking out tarmac and kerbs. These works will be stop by 11pm each evening and subsequent stages won't be as disruptive. Noise reduction measures will be put in place, such as acoustic matting, and noise levels will be routinely taken. Deliveries of materials to the tunnel will be managed early on each evening to limit the need for late night deliveries of paving slabs or kerbs.
This work is being carried out by local company McPhillips (Wellington) Ltd on behalf of Shropshire Council.
You can find out more about this work from our detailed timeline. If you'd like this information in a more accessible format, please get in touch.
Updates (latest update first)
Completion of work - summer 2025
The Station Gyratory Project is moving closer to completion, and whilst work is being completed on Castle Foregate and New Park Road in connection with the new shared footway/cycleway, arrangements are being made for the final surfacing of the roads both here and around the gyratory.
The nature of the work to replace the old road surface with a new one requires full road closures to be in place for safety reasons, and to ensure that the work can be completed as quickly as possible, reducing the impact to residents and businesses.
In order to minimise the disruption, work will be delivered overnight, between the hours of 8pm and 6am (see dates on this page). No weekend working is planned, and access for residents and businesses located within the closure will be controlled and maintained by operatives at the points where the road closures take effect.
The equipment that will be used is noisy, but the works will proceed as quickly as possible, with the more intrusive work, such as adjusting manhole and drain covers, being undertaken earlier on in the evenings. Daytime working has been considered, but given the location and volumes of traffic experienced during the day it would cause greater disruption and probably take far longer to complete.
For each closure, a fully signed diversion route will be in place, and access for residents, businesses and deliveries will be maintained. Copies of the diversion plans are attached to this page, entitled 'Diversion route 1-6'.
Letters are being issued to residents and businesses in the area. We apologise for any inconvenience, and appreciate your patience during this work.
Bus services have been taken into account, and the final service leaving the bus station at the end of each day will be able to continue its journey, which is the same arrangement that was implemented for the previous Cross Street night-time closures.
Taxis will be able to pick up and drop off at the railway station, under guidance and direction from the operatives at the points of closure. The operatives will all be wearing bodycam equipment, and registration plates will be checked.
The work is being carried out by local company McPhillips (Wellington) Ltd on behalf of Shropshire Council.
The work programme is as follows:
New Park Road and Castle Foregate (to Cross Street)
- Monday 7 and Tuesday 8 July - removal of old road surface
- Wednesday 9 July - adjusting manhole and drain covers
- Thursday 10 and Friday 11 July - lay new road surface
Station Gyratory
- Monday 21 July - removal of old road surface in Castle Foregate
- Tuesday 22 July - removal of old road surface in Smithfield Road
- Wednesday 23 - lay new road surface (in part) in Castle Foregate
- Thursday 24 July - lay new road surface (in part) in Castle Foregate / Howard Street junction / Castle Foregate and Smithfield Bus Station entrance junction
- Friday 25 July - lay new surface in Smithfield Road
- Monday 28 July - removal of old road surface in Chester Street, Ellesmere Road and Cross Street
- Tuesday 29 July - lay new road surface to part of Smithfield Road and part of Chester Street
- Wednesday 30 July - lay new road surface to part of Chester Street and Cross Street
- Thursday 31 July - lay new road surface on Ellesmere Road, part Chester Street and part Smithfield Road
Where possible, once the road surfacing work has been completed, the contractor will aim to lay the new road markings at the same time whilst the roads are closed. Additional time, up to 15 August, has been allowed should the need arise for road closures to complete this activity. A further update will be provided if extra road closures are required.
Shrewsbury Station Gyratory work to begin again 6 January
Newsroom article: